Restoration diary

Reports of restoration work on 50029 and 50030.

New sales items available!

​We are pleased to announce that a number of new models are available for you to purchase in order to support our project.​RRRG is able to supply brand new Hornby models at very competitive prices as well as some pre-owned models.  Our stock of pre-owned models tends to change quite rapidly and so we tend not to list them in our shop.  If...
Continue reading
2368 Hits
0 Comments

Website updates

​The first of what will hopefully be a few website updates over the coming days.  The most recent issues of the RRRG newsletter, issues 30 and 31, are now available to view.  Issue 31 is currently restricted to viewing by RRRG members until the next issue is released.Issue 29:Issue 30:Issue 31:
Continue reading
1728 Hits
0 Comments

Working party report 24th July 2016

​Dave Rolfe and I were on site today. Dave was freeing up one of the cab doors on Repulse while I carried on undercoating in the Thin Man's and over the cubicle inside the same locomotive.  Ian Kemp was on site the previous Saturday and they unbolted the remaining pipes and connections to the radiator fan currently inside 50030,...
Continue reading
2513 Hits
0 Comments

Working party reports May-June 2016

The battery charge diode reinstalled in the electrical cuible inside 50030 after testing and repair.
New volunteer Andy Blofield getting his hands dirty for the first time.
​29th May 2016Dave Rolfe was helping remove usable parts from an old coach which is to be sent for cutting, and he asked for any electrical items he could salvage. He got two small steel cabinets and several lengths of conduit plus various elbows and tees. The smaller of the two cabinets could be useful as a connection box for the severed conduit o...
Continue reading
2408 Hits
0 Comments

Working party reports April-May 2016

Refurbished fire bottles area inside 50030.
​18th April 2016I brought the good battery charge diode back and carried on cleaning and undercoating cubicle covers, scraped loose paint off the roof over the cubicle and finished re-threading the holes for the slotted covers right at the top of the cubicle.Dave Rolfe has cleaned and painted the area behind where the fire bottles stand next to the...
Continue reading
2014 Hits
0 Comments

Working party reports and updates January-April 2016

Battery charge diode ex-50030 (left) and a spare from RRRG stores (right). The ex-loco component gave suspect results during routine testing and both were taken for more in-depth tests courtesy of another group.
​A compilation of work party reports since our last updates.25th January 2016Dave Rolfe and Peter Carter continued to put the new oil into the ex-50008 power unit, I refitted the reverser actuator cylinder and checked out the battery charge diode again, which still gave strange readings, and re-threaded some more of the electrical cubicle cover hol...
Continue reading
2321 Hits
0 Comments

A host of updates coming soon...

Apologies for the radio silence folks.  RRRG hasn't shut down and ceased to exist.  It's more that we've been busy both on group matters and with our own personal lives.  A number of updates should follow later today.
Continue reading
1534 Hits
0 Comments

Work party reports 30th November 2015 and 17th January 2016

Work party reports 30th November 2015 and 17th January 2016
The reverser for 50030 with the air connection temporarily attached to the actuator. We successfully operated the air valves from an off board compressor to prove we had the correct connections.
On 15th November, Ian, Pete and Dave continued filling the power unit with the new oil, checking for leaks along the way, and blanking off pipes that cannot be fitted before the PU is lifted back into Repulse. Dom and I continued belling out the electrical cubicle wiring, and completed all the cables from the compressor, rad fan, ...
Continue reading
2854 Hits
0 Comments

Working party report 15th November 2015

Working party report 15th November 2015
Dave Rolfe, Peter Carter and Ian Kemp started filling the power unit with the new oil supplied by Morris Lubricants, checking for leaks along the way. I met and showed the prospective new welder what areas require his attention on Repulse, and also showed recent member Deborah Stokes more thoroughly round Repulse than I was able to do at the open d...
Continue reading
2400 Hits
0 Comments

Working party report 25th October 2015

Working party report 25th October 2015
The work party was attended by Dave Rolfe and myself plus Mark Burrows in the morning. Mark dropped off a set of cab desk panels for me to take a look at, then spent the rest of the morning searching through our stores of other cab parts. The panels appear to be in good condition but are missing the speedometer.  We have this item in stock els...
Continue reading
2859 Hits
0 Comments

Working party report 3rd October 2015

Working party report 3rd October 2015
Ian Kemp, Peter Carter and Dave Rolfe fitted two oil filter housings to the power unit,  and cut down a spare to make a further shallow one (which Dave welded up), so they can pump oil round the power unit when we get to that stage. I fitted three cubicle doors I had left to dry last work party, cleaned two large ones and topcoate...
Continue reading
3047 Hits
0 Comments

Working party report 20th September 2015

Ian Kemp, Peter Carter and Dave Rolfe removed pipework in Renown to get at, and remove, the fuel lift pump/alternator, which we need for Repulse, but not before it's been sent away for overhaul. (We often get asked why we don't strip Renown to help restore Repulse; the simple answer is that there isn't much on 50029 that we need for 50...
Continue reading
2351 Hits
0 Comments

Cab restoration update

At the last work party I attended I took home with me a number of items to repair/overhaul or look into replacements.The first items were a pair of air horn valves, two of which are our three spares.  Despite looking rather battered the first one (photo 1) was in generally good condition.  I stripped it down, gave it a good clean, sourced...
Continue reading
2399 Hits
0 Comments

Working party report 6th September 2015

A slightly frustrating day was had.  Ian, Dave and the mechanical team struggled all day to try and fit the last remaining piece of oil pipe to the power unit so they can pump oil round it, but despite cutting more and more off one of those big hardened steel plates holding the supporting sleepers together, they still co...
Continue reading
2189 Hits
0 Comments

Working party reports 26th July and 9th August

Working party reports 26th July and 9th August
Refitted oil (pink) and water (blue) pipes leading to the heat exchanger recently refitted to the 50008 power unit.
The oil filters and strainer were refitted to the power unit recently. The grey caps above the blue water pipe are the tops of the oil filter housing. One of these contains the strainer with the rest being filters.
Dave Rolfe continued to make progress cleaning out the air filtration compartment between the radiator and engine rooms.
The new CU5 radiator fan control unit was test fitted into 50030 and is seen alongside the CU7 ETH field detector unit.
On 26th July Pete and Ian rifled through our extensive spares collection to find pipework needed to refit to the ex-50008 power unit as its rebuild continues. I carried on refurbishing and painting the electrical cubicle doors and framework. I also rediscovered a large quantity of Class 56 electronic units that we had speculatively bought from scra...
Continue reading
2248 Hits
0 Comments

Working party reports 12th and 19th July 2015

Working party reports 12th and 19th July 2015

On July 12th, Mark Burrows went through our stores area sorting out the doors for the electrical cubicles of both locomotives, to see if any were missing, and if so, which ones. We seem to be missing just one small door for Renown. Ian Kemp, Pete Carter and Dave Rolfe refitted the heat exchanger onto the ex-50008 power unit, including the replacement end piece recovered from the power unit in Repulse. Dom Jackson assisted Andy Rowlands belling out cables inside the electrical cubicle of 50030, as part of the completion of the electrical system and in continued preparation for the first fire-up of the locomotive.  At the end of the day, Dave, Ian and Pete covered the PU with a new large tarpaulin as the old ones had started to deteriorate.

 

The work party on 19th July was attended by myself, Dave Rolfe, Peter Carter, Ian Kemp and Mark Burrows.  Mark spent most of the day making a start on clearing one of our sotrage areas, as its current location is required by Peak Rail to extend their engine shed.

At the last work party the heat exchanger was repaired, cleaned, painted and refitted to the ex-50008 power unit.  This allowed Dave, Pete, Ian and myself to refit the pipe work around it.  The main aim of the pipe fitting is to complete the oil lubrication system so we can hand prime the oil around the engine which will lower the risk of damage to the bearings when the engine is barred over. By the end of the day all of the main oil pipes had been fitted, except one which cannot be fitted as the sleepers that the power unit is sat on are in the way. We now need to order new oil filters before the filter housings can be fitted.  The main image for this entry shows the refitted heat exchanger together with the pipework we managed to reinstall during the work party.

I spent the afternoon assessing the cabs on Repulse with a view of restarting the repair work on them, then I made a start on checking what cab parts we have in store and what reusable parts are in the e- 50037 cab.

Continue reading
2436 Hits
0 Comments

Working party report 28th June 2015

Working party report 28th June 2015
This work party was attended by myself plus the "Three Amigos": Dave Rolfe, Ian Kemp and Peter Carter.  Dave and I fitted a couple more water and oil pipes to the ex-50008 power unit, I then swapped a water pipe from the power unit inside 50030 to replace a damaged one on the new power unit.
 
The main news from this Sunday centres around the heat exchanger which was removed from storage, due to the size and weight this was no mean feat but between the four of us and the use of our winch we managed to move it out for inspection. When we purchased the ex-50008 power unit we were told the heat exchanger had been swapped for the one currently in 50008 as it had a leak. When Ian inspected it, it was clear the end plate had corroded through in a couple of places (this plate is around 5mm thick so it's surprising it has rusted so badly). Thankfully the rest of the exchanger looks to be ok but we will need to pressure test it at some point. The rest of the afternoon was spent removing the end plate from the heat exchanger inside 50030; although this is quite rusty it appears to be in much better condition and should be easy(ish) to swap over.

 

 b2ap3_thumbnail_oil-pipe-and-gasket-med.jpg b2ap3_thumbnail_heat-exchanger-med.jpg 
Continue reading
2829 Hits
0 Comments

Don't forget our open afternoon!

Don't forget our open afternoon!

Don't forget, this coming Sunday (June 21st) is your chance to come along and inspect the RRRG project at close quarters!  See how we are getting on, chat to the team, find out how the money is being spent, discuss what we still need to do and how we plan to go about doing it!  Have a guided tour of the locomotives and the RRRG infrastructure.  Maybe find out how you could get involved?  Get your RRRG branded merchandise from our sales stand!  All this from 2 PM onwards at our Rowsley South, Peak Rail base, just off the A6 north of Darley Dale.  As it happens there is a vintage bus rally at Peak Rail that same day so you can just follow the crowds to find us!

Continue reading
2447 Hits
0 Comments

Working party report 31st May 2015

Working party report 31st May 2015

Ian Kemp, Peter Carter and Dave Rolfe carried on fitting oil, water and fuel pipework to the ex-50008 power unit, but on the side facing Renown, so no photo opportunities were possible today.

In preparation for the open day on June 21st, I washed down the outside of the electrical cubicle frame in 50030 and undercoated it, as it had become dirty from repeated handling since it was originally painted about five or six years ago. I also cleaned and undercoated the two cubicle doors from the fuse and MCB compartment. I brought three more cubicle doors home to clean.

b2ap3_thumbnail_010.JPG b2ap3_thumbnail_008.JPG 

Just a reminder that we are having our Open Day on the afternoon of Sunday June 21st where RRRG members will be on hand to give guided tours of the project and discuss progress. We hope to see you there!

Continue reading
2541 Hits
0 Comments

Working party report 24th May 2015

Working party report 24th May 2015

Ian Kemp, Peter Carter and Wes Needle continued fitting coolant and oil pipework to the power unit, while Dave Rolfe carried on painting the other side of the power unit.

a1sx2_Display_008.JPG

I removed the battery charge contactor so I could clean and undercoat the compartment where the CU2 and CU7 go, then did the same for the compartment underneath where the CU1 sits, in readiness for having them temporarily fitted for the open day. Topcoat will be applied next workparty. I also cleaned the dirtiest two of the cubicle doors ready for painting.

a1sx2_Display_005-2.JPG a1sx2_Display_006-2.JPG

Continue reading