RRRG new website top logo resized

 

Restoration diary

As one of RRRG's electrical officers I will write about my specialist field as well as general reports of work on site.

Work party report 15th May 2022

Work party report 15th May 2022

Mark Burrows, Jay Hirst and I were on site today.

Mark carried on painting air filter frames, while Jay and I continued belling out cables in the electrical cubicle.

Ian the welder had been on site last week, and had fitted new grip strips to the engine room and generator compartment floors where Mark had cut out the corroded sections, as seen in my photo below. He has also started reparing around the bottom of the air filter frames opposite the electrical cubicle.

Work party report 18th April 2022
Work party report 12th June 2022

Comments

 
No comments yet
Already Registered? Login Here
Guest
Friday, 15 November 2024

Captcha Image