Restoration diary

Reports of restoration work on 50029 and 50030.

Work party reports 30th November 2015 and 17th January 2016

Work party reports 30th November 2015 and 17th January 2016
The reverser for 50030 with the air connection temporarily attached to the actuator. We successfully operated the air valves from an off board compressor to prove we had the correct connections.
On 15th November, Ian, Pete and Dave continued filling the power unit with the new oil, checking for leaks along the way, and blanking off pipes that cannot be fitted before the PU is lifted back into Repulse. Dom and I continued belling out the electrical cubicle wiring, and completed all the cables from the compressor, rad fan, ...
Continue reading
3901 Hits
0 Comments

Working party report 25th October 2015

Working party report 25th October 2015
The work party was attended by Dave Rolfe and myself plus Mark Burrows in the morning. Mark dropped off a set of cab desk panels for me to take a look at, then spent the rest of the morning searching through our stores of other cab parts. The panels appear to be in good condition but are missing the speedometer.  We have this item in stock els...
Continue reading
3750 Hits
0 Comments

Working party report 3rd October 2015

Working party report 3rd October 2015
Ian Kemp, Peter Carter and Dave Rolfe fitted two oil filter housings to the power unit,  and cut down a spare to make a further shallow one (which Dave welded up), so they can pump oil round the power unit when we get to that stage. I fitted three cubicle doors I had left to dry last work party, cleaned two large ones and topcoate...
Continue reading
3972 Hits
0 Comments

Working party report 20th September 2015

Ian Kemp, Peter Carter and Dave Rolfe removed pipework in Renown to get at, and remove, the fuel lift pump/alternator, which we need for Repulse, but not before it's been sent away for overhaul. (We often get asked why we don't strip Renown to help restore Repulse; the simple answer is that there isn't much on 50029 that we need for 50...
Continue reading
3122 Hits
0 Comments

Cab restoration update

At the last work party I attended I took home with me a number of items to repair/overhaul or look into replacements.The first items were a pair of air horn valves, two of which are our three spares.  Despite looking rather battered the first one (photo 1) was in generally good condition.  I stripped it down, gave it a good clean, sourced...
Continue reading
3245 Hits
0 Comments

Working party report 6th September 2015

A slightly frustrating day was had.  Ian, Dave and the mechanical team struggled all day to try and fit the last remaining piece of oil pipe to the power unit so they can pump oil round it, but despite cutting more and more off one of those big hardened steel plates holding the supporting sleepers together, they still co...
Continue reading
2928 Hits
0 Comments

Working party reports 26th July and 9th August

Working party reports 26th July and 9th August
Refitted oil (pink) and water (blue) pipes leading to the heat exchanger recently refitted to the 50008 power unit.
The oil filters and strainer were refitted to the power unit recently. The grey caps above the blue water pipe are the tops of the oil filter housing. One of these contains the strainer with the rest being filters.
Dave Rolfe continued to make progress cleaning out the air filtration compartment between the radiator and engine rooms.
The new CU5 radiator fan control unit was test fitted into 50030 and is seen alongside the CU7 ETH field detector unit.
On 26th July Pete and Ian rifled through our extensive spares collection to find pipework needed to refit to the ex-50008 power unit as its rebuild continues. I carried on refurbishing and painting the electrical cubicle doors and framework. I also rediscovered a large quantity of Class 56 electronic units that we had speculatively bought from scra...
Continue reading
3080 Hits
0 Comments

Open Day 21st June 2015

Open Day 21st June 2015

Renown Repulse Restoration Group is holding an Open Day on Sunday 21st June 2015 from 2 PM onwards at our Rowsley South, Peak Rail base.  We hope to attract new volunteers and investment into our project.  All are welcome, whether experienced preservationists or complete beginners!  RRRG members will be on site to show you around 50029 and 50030, as well as discuss our facilities, restoration plans and how you can help as a future volunteer for RRRG.  We look forward to seeing you then and there.  Peak Rail are also hosting a classic bus event on the same day, providing an additional attraction for visitors to the railway.

Continue reading
3580 Hits
0 Comments

Working party report 19th April 2015

Working party report 19th April 2015

During the work party of 19th April Andy Rowlands connected up the reverser air piston coils and tidied up the cables in the electrical cubicle in 50030, then started investigating the severed cables under the main cubicle walkway. They appear to be from the DSD relay box but further investigation will be required to trace them exactly.

b2ap3_thumbnail_004.JPG b2ap3_thumbnail_006.JPG

Peter Carter and Ian Kemp together with Dave Rolfe continued fitting oil and water pipes to the ex-50008 power unit (see previous report, Power unit progress) in continued preparation for its use inside the overhauled 50030.

b2ap3_thumbnail_009.JPG b2ap3_thumbnail_010.JPG

 

Continue reading
3603 Hits
0 Comments

Work party report 21st September 2014

Work party report 21st September 2014
Dave, Pete and Ian disconnected and removed the four sections of airshaft round the power unit flywheel and bolted up the second intercooler, which Dave then painted. I continued cutting and fitting cubicle air pipes, removed the Z23 resistor and a now-redundant cable from it to the CU6, in preparation for fitting an electronic device in its place as part of the CU6 upgrade.
 
As we were packing up we were greeted by the sound of eight Rolls Royce Merlins as both the preserved airworthy Lancasters flew over Rowsley.
Continue reading
5871 Hits
2 Comments

Spare electrical cubicle progress

Spare electrical cubicle progress

If you have been following RRRG for some time, you will remember that about a year ago we purchased and collected a number of spare electrical parts from the owners of 50021 Rodney.  Amongst these was the electrical cubicle originally in 50011 Centurion before that locomotive was scrapped.  Our reason for purchasing the cubicle was to use as a donor for rebuilding 50029's cubicle; as a rule of thumb the items that were removed from 50030 before we bought the locomotive were carefully unscrewed and the wiring in the electrical cubicle was in good condition.  The same cannot be said for 50029 unfortunately, with many of the cubicle wires having been cut.  To save the headache of pairing loose ends we aim to transplant the relatively intact wiring loom from the ex-Centurion cubicle into 50029.  That there were a good number of other components in the donor cubicle that would be useful for 50029 was a bonus.  The actual frame of the ex-50011 cubicle is however not in such good condition as the cubicle frame already in 50029: many of the catches for the doors are either bent or broken and it is obvious the cubicle has led a hard life since the locomotive it resided in was scrapped.  For this reason we cannot just swap the cubicles around between Renown and Centurion and a process of making one good one from two halves is necessary.

These pictures were taken on 9th June 2013 and show progress on the careful stripping of this cubicle and some of the parts we have recovered from it.  Electrical volunteers Steve Tripp and Andy Rowlands are shown at work but credit must also go to Julie Rollason and Sarah McCall for their invaluable assistance with this sub-project.

b2ap3_thumbnail_ST-cubicle-blog-image.JPG

b2ap3_thumbnail_AMR-ST-elec-cubicle-small.JPG


The complexity of the wiring loom is obvious from these pictures which show volunteers Steve Tripp and Andy Rowlands removing some of the last major components before we make a decision on how to tackle the wiring loom.  A good number of useful items have been recovered from this cubicle for re-use in 50029, as shown below.

 b2ap3_thumbnail_lighting-delay-timer.JPG  b2ap3_thumbnail_kv10-ex-50011-small.JPG

Shown below is one of the cubicle doors from the ex-50011 cubicle.  We have already refurbished the equivalent door and installed into 50030 and we have a better example in stock for 50029.  This is actually one of the better condition parts of the cubicle frame and speaks to the state that the ex-50011 electrical cubicle is in.

b2ap3_thumbnail_Rotary-switch-elec-cubicle-door-ex-50011-small.JPG

The next task is to assess the wiring loom in the 50011 cubicle and how best to remove it.  As the pictures show it is a many-tentacled monster and will require considerable thought as to the best way forward before we dispose of the frame of the 50011 cubicle.  With the size of the "thin man's passage" inside a 50 round the side of the electrical cubicle now not befitting our volunteers' physical profiles, we may also look to lifting the cubicle out of 50029 as a way of proceeding.

Continue reading
7906 Hits
0 Comments

Workparty report for 2nd September 2012

Today I are be mostly...sorry been watching too many episodes of the Fast Show. Dave had spent the week on site as he's still off work following his operation & he's cleaned & painted most of the water & air inlet piping for the ex-008 power unit. Mark B dug out of the stores the two sections of protective shields for the A side generator conduits & cleaned and undercoated them; one each for 29 & 30. He also sorted a third section of the gen conduits, loosened off the joints and began removing years of layers of paint. I and my girlfriend Julie belled out and marked both sets of wiring from the cab AWS sunflowers to the AWS relay box, though removing the lid of the relay box proved difficult as two of the fixing bolt heads had been broken off some time ago, and I had to put an angle-grinder through the one stud to release the lid. I brought away the shaped mounting bracket from No.2 cab and the sunflower dial from No.1 cab to clean the contacts.

Continue reading
6833 Hits
0 Comments

Workparty report 12th August 2012

Ian & Pete cleared various debris out of the sump of the power unit, and started cleaning & painting sections of inlet air piping. Dave...supervised, as he is still recovering from being under the knife for a hernia and is excused duties for the moment. Mark cleaned & sorted another section of conduit for the generators, to go with the two sections he had previously done, so three down, 13 to go. This is not as easy as it sounds, as most of the lengths of conduits had been separated from each other for easier storage, so it was a case of multiple visits inside Repulse & our stores to find the right sections.

I test-fitted one of the new Z70 resistors, and found it fits the existing brackets perfectly. I just need to properly space the tapping bands, then it can be fitted permanently.

Continue reading
3394 Hits
0 Comments

Collecting gas bottles

Gas bottles on trolley

Our gas bottles on the trolley used to collect them; oxygen (black) and acetylene (maroon).

One of those "must get round to doing that sometime" tasks hanging over RRRG has been to collect a couple of cylinders of oxygen and acetylene with which to power our cutting and welding equipment. Although there is a BOC distributor just across the A6 from Peak Rail's Rowsley South site they have limited opening hours which are somewhat inconvenient for the regular on site RRRG volunteers.  Tim and I decided we would head up to Rowsley last Friday night in order to be on site in the morning ready to collect the gas. So, shortly after 4 o'clock on Friday afternoon I hit the road to drive the 170 miles or so from Reading to deepest Derbyshire whilst Tim got a train from Peterborough to Matlock, where I would meet him. I got delayed by the usual Friday traffic whilst Tim got delayed when 66008 decided to investigate the ballast on the Midland main line near Duffield. (I did however make it through Bletchingdon on the A34 without incident after my two year anniversary earlier this month, and once on site, Dave was as helpful and complimentary as ever that my latest car was retaining its factory-fitted styling so well).

The cylinders are now in situ at RRRG headquarters. One of the main uses we will have for them is to heat up some bolts and pins on our spare bogies which are absolutely stuck fast and won't shift any other way.  In particular there are some arms secured by pins and bolts which prevent the traction motors being removed from the bogies and we want to either free these off, or if necessary, cut them off (we have plenty of spares) in order to free the motors for removal to Bowers for overhaul.


Intake manifolds

Aluminium air intake manifolds destined for the ex-50008 power unit. The foreground example awaits the removal by wire brushing of years of dirt and grime to reach the standard of the background pair, which Dave Rolfe described as "Rolls Royce quality"!


Air intake manifolds with red oxide primer

After treatment with the wire brush, Tim and I set about red oxide primer coating of the manifolds we treated that day, as well as returning to some that other RRRG volunteers had already treated, just to ensure that "Rolls Royce finish"!

With the main excitement of the morning over, and after a few steadying cups of tea and brunch at the Peak Rail cafe, Tim and I set to work on wire brushing and red oxide painting of a number of air intake manifolds destined for the ex-50008 power unit. Chris Bodell's nascent music career meant he was playing a gig in Bakewell on Saturday night so he went home to practice and took his leave of us. Tim was diagrammed for transporting teenagers to a roller disco in Peterborough that evening and so, despite building up some momentum on the inlet manifolds, we reluctantly packed up and I drove us the 100 or so miles back to Peterborough, where the teenagers were transported and Tim and I undertook a mutual debriefing session in The Moorhen at Hampton Vale (Tim's local). Sunday was spent doing more work on the soon-to-be-launched new RRRG website (of which more in due course) and I then hit the road for the final time back to Reading, which was covered in a personal best time of 1 hour 50 minutes and brought my mileage for the weekend to a touch short of 400. But it's all good fun (allegedly!).

Continue reading
6673 Hits
0 Comments

Recovering parts acquired from Rodney Group

A large amount of heavy boulders blocking the path to the container where our purchased spares were.

On Friday 29th June 2012, Sarah and myself set off together with our trusty hound Toby to meet up with the contacted transport company at a site near Worcester to collect electrical items we had purchased from 50021 Rodney Group, this also included a Radiator Fan Motor and Traction Motor Blower for the D400 Fund.

When we arrived at site, we introduced ourselves to the Lorry Driver Nigel Chapman. The first problem we encountered was that due to the heavy deluge the day before, a delivery of large boulders had been delivered and dumped in front of the grounded curtain-sided truck body that our items were being stored in.

After a little head scratching it was decided we could get into the other side of the body if we removed the site security fencing. When we obtained access to the other side of body, the next obstacle was to release the tensioning mechanism, which through the passage of time had sunk into the ground, and after some digging with spades and persuasion with the site dumper truck which lifted the sunk body out of the ground we gained access.

We moved some fencing to gain access to the other side of the container.

With the transport lorry manoeuvred into position and stabiliser legs down the next problem encountered was a temperamental hydraulic hi-ab which with the technical know-how of Nigel, eventually played ball. The first two items strapped up and lifted out were the Cubicle and Rad Fan Motor. The two compressors and traction motor followed soon after. The items were secured down and we then drove to where the traction motor blowers and spare power unit (ex-50045) were stored. One blower motor was lifted and secured down.

We needed the site dumper truck to force our way in...


RRRG's main purchase, the electrical cubicle, safely loaded onto the lorry.

Once everything was checked to be secure we set off on our journey North, up the M5, M42 etc heading for Derbyshire with Bowers Electrical being our first port of call. We had anticipated the journey to be difficult with the usual Friday afternoon traffic, however also had the added problem of road closures along the A6 between Derby and Rowsley due to the Olympic Torch relay, fortunately the journey went without delay or incident. At Bowers we had the assistance of a forklift and very quickly off-loaded D400 Fund's Rad Fan Motor and Blower Motor together with our two compressors.

RRRG's haul included two genuine Class 50 compressors, ex-50011, seen being guided onto the lorry.


We then set off for Rowsley, arriving at site about 4:45pm, where we were met by local “BG” resident Dave Rolfe. Once on site we discovered one of our ETH generators (in worse condition than the others, which is why it was never sent for overhaul) was obstructing the route of the lorry to our storage shed, incidentally we also needed this moving, so with the Hi-ab on site we took advantage and relocated it dropping it near Renown together with the Traction Motor.

A further spare traction motor was also included in the deal.


A short break was had whilst we retired to the BG for a brew. Once refreshed we returned to our storage shed to off-load the electrical cubicle although this was not without problems as the hi-ab could not manoeuvre the cubicle all the way into the shed so with a solid steel bar and some brute force we pushed the cubicle in. Space in the shed being what it was, we had to man-handle the cubicle in at an angle until the doors could be closed and locked.  Everything was then sheeted up, secured and we eventually left for site calling at Frankie & Bennies for a very well earned bite to eat and pint, eventually getting back home some 15 hours after starting out earlier that morning.

After some manhandling to make it fit the available space inside RRRG's designated facility, the newly-purchased cubicle was safely stored awaiting future work. With this final act, a long and satisfying day finally came to an end!

A big thank you to Nigel Chapman the jovial lorry driver, who was a tremendous help on the day, enjoy your retirement!!  Photos by Sarah McCall.

Continue reading
29496 Hits
4 Comments

Work on site 1st April

I found another 10-12 conduit and pipe clamps that I need for in the generator room. I cleaned these up with wet and dry sandpaper and a wire cut brush, then white spirited them and painted them. Also put another coat of paint on the 40-odd clamps that I did last time I was on site.

I also re-secured 50029’s tarpaulin which was loose and flapping around a bit on one corner.

Dave Rolfe was on site as usual and continued with painting a second coat of paint onto the radiator grilles.  I took a few photos and noted how good they were looking; we will share these here soon.

Continue reading
5435 Hits
0 Comments

Workparty March 25th 2012

Dave was on site all weekend working on cleaning and painting one of the bodyside radiator grilles.



Ian and Pete with some assistance from Dave continued working on the ex-50008 engine replacing some of the head covers.



Steve and Sarah assessed traction motor contactor arc-chutes so spares and paxolin to replace missing parts can be ordered.



The long process of verifying all the cables from the electrical cubicle to equipment in 50029 was started. Each cable was to be tested with a multi-meter to confirm continuity. The first cables checked were those from terminal bar TB6 with blower No1 cables testing out ok. Problems were then encountered as we checked Blower No2 but could get no reading and eventually realised this was because the cables and flexible conduit had been cut about an inch from the connection box.



As it is too difficult to pull any slack through we have decided to dismantle the conduits with a view to reinstalling via a shorter route up the front of the blower negating the need to replace the cables.

Continue reading
4649 Hits
1 Comment

Workparty report for weekend 17th & 18th March.

Tom prepared the cab vestibule at no 2 end for repainting and carried out repairs to ceiling trims. new cab light frames were cut and replacement lights fitted.  Chris unseized the bolts securing the rad fan ducting to the fan motor and freed off the rad fan securing nuts. Doesn't sound much but all are captive and rusted solid so needed considerable work to avoid shearing and drilling out later.

Tim & Dom continued buzzing the surface rust and grime off the brake rigging that had been selected by Chris and Dave for use on the bogie overhauls.  The pile of "to do" components is now virtually nothing and Dom got a very nice facial treatment out of it as well, after which he discovered the shower in the Peak Rail shed is stored unserviceable. Tim took to the bits of rigging Dom had done to clean the areas he couldn't reach, using a drill as opposed to the wire cup brush Dom had. Following this and an unexpected appearance by Chris Bodell the two of them dragged the cleaned-up rigging to join the rest of it in an undercover location.  There they sprayed the pieces with light oil in order to preserve them until we start reassembling the bogies.

I only attended on Sunday, and with the length of the committee meeting, I only had time to fit the last missing shaped copper bar I had made, which goes from the reverser to no.2 traction motor contactor.

Continue reading
3965 Hits
0 Comments

Work party 17-18 March

We will be on site the weekend of 17-18 March to continue restoration work. Anyone in the area is welcome to drop by and say hello although we are planning to have a Committee meeting on Sunday which may take up a good few hours with much to discuss.

Continue reading
3818 Hits
0 Comments

On site activity 25-26 Feb

A good attendance this last weekend, others will contribute their own reports in due course. New volunteer James Andrews arrived on Saturday for his first working party and we were also blessed with the presence of Paul Sturm on an impromptu trip from the Netherlands. Dave Rolfe was the usual permanent fixture on site as Tim and I arrived at about midday on Saturday. Later on Sunday we were joined by Mark Burrows, Ian Kemp and Peter Carter.

Tim, Paul and I concentrated on the continued cleaning of brake rigging equipment where a large stash was extracted from storage:

Dirty brake rigging to be cleaned by Paul Sturm and myself.




;

Although not in the "Chris Thorn" level of restoration skill the wire brushing of these took much elbow grease and many cups of tea and ready meals during the day. The gradual accumulation of brushed parts into a pile for Tim to hone with the smaller drill was quite satisfying:

Brake rigging cleaned with large wire brushes by Paul Sturm and myself, ready for Tim to hone with the smaller drill.




Meanwhile Dave and James had removed one of the adjustable radiator louvres from 50030 with a view to getting the shutters to work again. The linkage was seized utterly solid and heavily rusted. However Paul brushed it up and when Ian arrived on Sunday their combined efforts made for an amazing transformation:

The rusted, seized radiator linkage after brushing up by Paul Sturm and treatment by Ian Kemp with a little used engine oil.




Elsewhere, Dave, obviously heartened by the success on one radiator grille, removed the other one for similar treatment (but did reinstall it before the end of the weekend).

Dave repairing the other opening radiator louvre on 50030 following attention to its companion the previous day.






All in all this was a very productive weekend and I look forward to the next working party.

;

Continue reading
4088 Hits
1 Comment