Pete & Ian attempted to refit the first of the large new shell bearing caps onto the piston conrod they inserted into the block last time using the traditional method of a piece of rope suspending the cap beneath the crank shaft to align it. However, even with much greater room with the power unit out of the loco, this proved difficult, so they devised a tool to aid them, which worked well & the cap was successfully mated to the conrod. No electrical work was undertaken as Chris T, Chris B, Tim & Dom & I amalgamated the items in the coach into 50 & non-50 parts & cleared one side of the coach for racking from the container. We then cleared one section of racking in the container, dismantled it & reassembled it in the coach & transferred the electrical parts into the coach. Tim & Dom also removed the rubbish mentioned last time from the coach into the PR skip.